This chapter provides an architectural oversight of the implementation.
Figure: Phase G: Implementation Governance
Objectives
The objectives of Phase G are:
-
To formulate recommendations for each implementation project
-
To govern and manage an Architecture Contract covering the overall implementation and deployment process
-
To perform appropriate governance functions while the solution is being implemented and deployed
-
To ensure conformance with the defined architecture by implementation projects and other projects
-
To ensure that the program of solutions is deployed successfully, as a planned program of work
-
To ensure conformance of the deployed solution with the Target Architecture
-
To mobilize supporting operations that will underpin the future working lifetime of the deployed solution
Approach
It is here that all the information for successful management of the various implementation projects is brought
together. Note that, in parallel with Phase G, there is the execution of an organizational-specific development
process, where the actual development happens.
To enable early realization of business value and benefits, and to minimize the risk in the transformation and
migration program, the favored approach is to deploy the Target Architecture as a series of transitions. Each
transition represents an incremental step towards the target, and each delivers business benefit in its own right.
Therefore, the overall approach in Phase G is to:
-
Establish an implementation program that will enable the delivery of the Transition Architectures agreed for
implementation during the Migration Planning phase
-
Adopt a phased deployment schedule that reflects the business priorities embodied in the Architecture Roadmap
-
Follow the organization's standard for corporate, IT, and architecture governance
-
Use the organization's established portfolio/program management approach, where this exists
-
Define an operations framework to ensure the effective long life of the deployed solution
Phase G establishes the connection between architecture and implementation organization, through the Architecture
Contract.
Project details are developed, including:
-
Name, description, and objectives
-
Scope, deliverables, and constraints
-
Measures of effectiveness
-
Acceptance criteria
-
Risks and issues
Implementation governance is closely allied to overall architecture governance, which is discussed in Part VII, Architecture Governance .
A key aspect of Phase G is ensuring compliance with the defined architecture(s), not only by the implementation
projects, but also by other ongoing projects within the enterprise. The considerations involved with this are explained
in detail in Part VII, Architecture Compliance .
Inputs
This section defines the inputs to Phase G.
Reference Materials External to the Enterprise
Non-Architectural Inputs
Architectural Inputs
-
Organizational Model for Enterprise
Architecture, including:
-
Scope of organizations impacted
-
Maturity assessment, gaps, and resolution approach
-
Roles and responsibilities for architecture team(s)
-
Constraints on architecture work
-
Budget requirements
-
Governance and support strategy
-
Tailored Architecture Framework, including:
-
Tailored architecture method
-
Tailored architecture content (deliverables and artifacts)
-
Configured and deployed tools
-
Statement of Architecture Work
-
Architecture Vision
-
Architecture Repository, including:
-
Re-usable building blocks
-
Publicly available reference models
-
Organization-specific reference models
-
Organization standards
-
Architecture Definition Document
-
Architecture Requirements Specification,
including:
-
Architectural requirements
-
Gap analysis results (from Business, Data, Application, and Technology Architectures)
-
Architecture Roadmap
-
Transition Architecture, including:
-
Implementation Governance Model
-
Architecture Contract (standard)
-
Request for Architecture Work identified during
Phases E and F
-
Implementation and Migration Plan
Steps
The level of detail addressed in Phase G will depend on the scope and goals of the overall architecture effort.
The order of the steps in Phase G (see below) as well as the time at which they are formally started and completed
should be adapted to the situation at hand in accordance with the established architecture governance.
The steps in Phase G are as follows:
-
Confirm Scope and Priorities for Deployment with Development Management
-
Identify Deployment Resources and Skills
-
Guide Development of Solutions Deployment
-
Perform Enterprise Architecture Compliance Reviews
-
Implement Business and IT Operations
-
Perform Post-Implementation Review and Close the Implementation
1. Confirm Scope and Priorities for Deployment with Development Management
2. Identify Deployment Resources and Skills
The project resources will include the development resources which will need to be educated in the overall enterprise
architecture deliverables and expectations from the specific development and implementation projects.
The following considerations should be addressed in this step:
-
Identify system development methods required for solutions development
-
Note:
-
There are a range of systems development methods and tools available to the project teams. The method
should ideally be able to interoperate with the architecture outputs; for example, generate code from
architecture artifacts delivered to date. This could be achieved through the use of modeling languages used
for the enterprise architecture development that may be captured as inputs to the systems development tools
and thereby reduce the cost of solutions development.
-
Ensure that the systems development method enables feedback to the architecture team on designs
3. Guide Development of Solutions Deployment
4. Perform Enterprise Architecture Compliance Reviews
-
Review ongoing implementation governance and architecture compliance for each building block
-
Conduct post-development reviews
-
Close development part of deployment projects
5. Implement Business and IT Operations
-
Carry out the deployment projects including: IT services delivery implementation; business services delivery
implementation; skills development & training implementation; communications documentation publication
-
Publish new Baseline Architectures to the Architecture Repository and update other impacted repositories, such as
operational configuration management stores
6. Perform Post-Implementation Review and Close the Implementation
-
Conduct post-implementation reviews
-
Publish reviews and close projects
Closure on Phase G will be when the solutions are fully deployed once.
Outputs
The outputs of Phase G are:
-
Architecture Contract (signed), as recommended in the architecture-compliant
implemented architectures
-
Compliance Assessments
-
Change
Requests
-
Architecture-compliant solutions deployed including:
-
The architecture-compliant implemented system
-
Note:
-
The implemented system is actually an output of the development process. However, given the
importance of this output, it is stated here as an output of the ADM. The direct involvement of
architecture staff in implementation will vary according to organizational policy, as described in
Architecture Governance .
-
Populated Architecture Repository
-
Architecture compliance recommendations and dispensations
-
Recommendations on service delivery requirements
-
Recommendations on performance metrics
-
Service Level Agreements (SLAs)
-
Architecture Vision, updated post-implementation
-
Architecture Definition Document, updated post-implementation
-
Transition Architecture, updated post-implementation
-
Business and IT operating models for the implemented solution
|